Enterprise Way Loading Dock

The redevelopment at 12949 Enterprise Way removed portions of an operating warehouse for new and relocated truck docks and reconfigured the parking lot, disturbing 2.11 acres of a 24.75-acre facility in the Cowmire Creek watershed. Disturbance over one acre triggered post-construction Best Management Practices under the regional MS4 permit.

G&W handled the full civil scope: on-site parking, new loading docks, storm utilities, grading, and erosion control. The existing open detention basin came out, replaced by an underground system beneath expanded parking along Enterprise Way, providing channel and flood protection and recovering the basin footprint for parking. A hydrodynamic separator was paired with it, and the basin discharges to the existing 24-inch storm sewer running southeast to Cowmire Creek. Design carried a 15-year storm event with a 100-year overland flow path, then went through MSD and City review to permit.

Location:
Bridgeton, MO

Client Type:
Owner

Size:
24.75 acre site |
2.11 acres of disturbance

Market:
Industrial

Services Provided:
Civil Site Engineering

OUR APPROACH

Threshold Review

Disturbance area verified against MS4 permit requirements

Stormwater Design

Underground detention sized for a 15-year storm event

Overland Flow

100-year flow path routed across the site

Civil Document Set

Grading, erosion control, utilities, and storm profiles produced

Agency Coordination

Drawings reviewed and conformed through MSD and the City

DESIGN CRITERIA

MSD MS4 Permit

Post-construction BMPs triggered above one acre of disturbance

Post-Construction BMP

Underground detention and a hydrodynamic separator serving 2.11 acres

15-Year Storm

Detention system sized to the design event

100-Year Flow Path

Overland routing verified across the site