McConnell AFB Building 57

Air barrier work on a secured military installation carries verification demands that go beyond a typical commercial project, and the barrier itself only earns confidence once its bond to the substrate is measured rather than assumed. On a building where the enclosure was already installed, testing while the assembly remained accessible was the way to confirm the work held.

G&W conducted pull-off adhesion testing on the installed air barrier across six locations during a single site visit, measuring bond strength of the barrier materials to their substrates per ASTM D4541 and ABAA T002. A written report documented test locations, observed conditions, and results. Work was coordinated around base access and escort requirements to keep the single mobilization efficient.

Location:
Wichita, KS

Client Type:
General Contractor

Testing Scope:
Air barrier, 6 test areas

METHODS & STANDARDS

ASTM D4541

Barrier bond strength to substrate

ABAA T002

Air barrier assembly bond verified

OUR APPROACH

Access Coordination

Base escort scheduled around single mobilization

Test Layout

Six locations across installed barrier

Pull-Off Testing

Bond strength measured at each location

Substrate Evaluation

Results grouped by material and substrate

Reporting

Locations, conditions, and results documented